Penerapan Metode CPM (Critical Path Method) dalam Manajemen Servis Ganset Caterpillar di PT. Sigma Quantum Insani Balikpapan Kalimantan Timur
DOI:
https://doi.org/10.61132/mars.v3i4.921Keywords:
Generator Set Service Management, Critical Path Method (CPM), Project Scheduling, MS Project Application, Time Efficiency in MaintenanceAbstract
Generator Set Service Management is the process of organizing maintenance, repair, and upkeep activities of generator sets, starting from planning, implementation, evaluation, control, and improvement of services to ensure the generator machine continues to operate effectively and efficiently. The research was conducted at PT. Sigma Quantum Insani, located in Balikpapan, East Kalimantan. The problem addressed in the research is the frequent delays in completing scheduled tasks within the generator set service management activities. The purpose of the study is to determine the critical path of activities and identify the duration of the critical path. From the analysis using the Critical Path Method (CPM) assisted by MS Project software, the identified critical path activities are: A1-B1-B2-B3-B4-B5-B6-B7-B8-B9-B10-B14-B16-B17-C1-C2-D1-D2-D3, which include DO approval, engineering scope, painting scope, and delivery scope. The total time obtained for the critical path is 38 days, resulting in a time efficiency of 8 days in the generator set service process.
References
Akhmad, D. (2017). Materi kuliah manajemen proyek (pp. 1–24). Academia. https://www.academia.edu/34987359/MP_Pengertian_Work_Breakdown_Structure
Anindyadevi, A. (2022). Gantt chart adalah, manfaat komponen dan cara buatnya.
Fajar. (2009). Pengertian CPM dan PERT (pp. 10–12).
Fikri, A. A., & Luthan, P. L. A. (2021). Analisa penjadwalan main work dengan metode CPM dan PDM pada proyek jalan tol Tebing Tinggi-Parapat. Jurnal Engineering Development, 1(1), 7–15.
Husen, A. (2009). Manajemen proyek: Perencanaan, penjadwalan dan pengendalian proyek. Andi.
Kakaç, S., & Yener, Y. (2018). Cooling of electronic systems. CRC Press.
Kurniawan, S. (2019). Makalah Work Breakdown Structure (WBS), OBS, CBS. Scribd. https://www.scribd.com/document/437354996/Makalah-Wbs-Obs-Cbs
Nugrahani, P. P. (2018). Makalah manajemen proyek (pp. 1–24). Scribd. https://www.scribd.com/document/393423454/MAKALAH-MANAJEMEN-PROYEK#
Pinedo, M. L. (2012). Scheduling: Theory, algorithms, and systems (4th ed.). Springer.
Project Management Institute. (2013). A guide to the project management body of knowledge (5th ed.). PMI.
Supian PDAM. (2019). Jenis fitting. http://supianpdam.com/w2/jenis-fitting.html
Telaumbanua, T. A., Mangare, J. B., & Sibi, M. (2017). Perencanaan waktu pelaksanaan proyek konstruksi (Studi kasus proyek pembangunan gedung di Kabupaten Bandung) [Skripsi, Universitas Udayana].
Tom, M. (2018). Generator handbook: A practical guide to understanding and using generators. Academic Press.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 Mars : Jurnal Teknik Mesin, Industri, Elektro Dan Ilmu Komputer

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.