Implementasi dengan Metode Cpm-Pert Terhadap Penjadwalan Proses Produksi Conveyor Table Top Chain pada CV. Adikarya Teknik Sidoarjo

Authors

  • Erwin Saputro Universitas 17 Agustus 1945 Surabaya
  • Handy Febri Satoto Universitas 17 Agustus 1945 Surabaya

DOI:

https://doi.org/10.61132/mars.v3i1.644

Keywords:

Production Delays, Conveyor Table Top Chain, CPM, PERT, Operational Efficiency

Abstract

Cv. Adikarya Teknik is one of the manufacturing companies engaged in the field of mechanical engineering that produces wire mesh and conveyor table top chains. Cv. Adikarya Teknik has 6 projects that did not meet the 2024 work targets, resulting in delays in the completion of Conveyor Table Top Chain products. The delays are quite significant, with the work for Aqua Mineral Water being delayed by 11 days and Pocari by 10 days. Production analysis using the CPM and PERT methods to identify priority issues of delay risks and improve operational efficiency. By using the CPM method, it was found that the critical path of the Conveyor Table Top Chain production project lies in activities A-B-C-E-F-G-H-I-J-K-L-M-N (all located on the critical path). There is slack in activity D (Incoming Material); if it is delayed, it will not affect the critical path activities. The results of the PERT method on the Conveyor Table Top Chain project show that the probability of the conveyor production project being completed faster than the usual time, which is within a duration of 127 days, is 84%.

References

Alwi, M. A., & Syahrizal, I. (2015). Analisis penerapan sistem penjadwalan CPM, PERT, dan LOB pada penjadwalan proyek (Studi kasus: Pembangunan gedung kantor PT. Jasa Asuransi Indonesia – Pematang Siantar). Jurnal Teknik Sipil USU, 1–13.

Julian, D. M., Sutrisno, S., & Basri, A. A. (2023). Penerapan metode CPM dan PERT pada proyek pembangunan drainase di Perum Cengkong guna mempercepat waktu penyelesaian (Studi kasus: CV XYZ). Jurnal Serambi Engineering, 8(1), 4781–4788.

Larson, E., & Gray, C. (2014). Project management: The managerial process (6th ed.). McGraw Hill.

Qomariyah, S., & Hamzah, F. (2013). Analisis network planning dengan CPM (Critical Path Method) dalam rangka efisiensi waktu dan biaya proyek. Jurnal Teknik Sipil USU, 1(4), 408–416.

Santoso, B. (2003). Manajemen proyek. Yogyakarta: Penerbit Graha Ilmu.

Tamalika, T., & Fuad, I. S. (2022). Analisis penjadwalan waktu pekerjaan proyek Poltekkes jurusan farmasi tahap I dalam perspektif manajemen proyek. Jurnal Pendidikan Tambusai, 6(1), 8207–8214. https://jptam.org/index.php/jptam/article/view/3685

Teras, D., Tjahjono, B., Islamy, M. R., Seruyan, P., Seruyan, P., & Seruyan, P. (2024). Jurnal Penelitian Jalan dan Jembatan, 4, 11–21.

Wiranda, F. I., & Murnawan, H. (2024). Manajemen proyek pengerjaan pipa air pada PT. X menggunakan metode CPM dan PERT. Jurnal Teknik Industri Terintegrasi, 7(2), 1139–1146. https://doi.org/10.31004/jutin.v7i2.28508

Downloads

Published

2025-01-14

How to Cite

Erwin Saputro, & Handy Febri Satoto. (2025). Implementasi dengan Metode Cpm-Pert Terhadap Penjadwalan Proses Produksi Conveyor Table Top Chain pada CV. Adikarya Teknik Sidoarjo . Mars : Jurnal Teknik Mesin, Industri, Elektro Dan Ilmu Komputer, 3(1), 156–164. https://doi.org/10.61132/mars.v3i1.644